Why I don’t want every engineering day committed
When every engineering day is promised to project work, routine production problems require someone to break that promise. Planning requires room for both.
By the time engineering teams finish planning, leaving time unassigned often feels like something that requires an explanation. There’s always another project waiting, and putting it on the roadmap looks more productive than admitting that we don’t know exactly what will happen in production next week.
I’m much more comfortable with that admission than with committing every available day. If teams own running services, their plans require room for work they haven’t identified yet, and that room has to survive the next request to squeeze something in. Otherwise, ordinary production problems require engineers to break promises we probably shouldn’t have made.
The work arrives whether we plan for it or not
Say we have twenty engineer-days available for a planning period, after meetings and known absences. We commit all twenty to projects, then a production issue requires two engineers for a day. Even if the estimates were perfect, we’re now two days behind. We haven’t included whatever time it takes to get back into the interrupted work.
Reserving two days wouldn’t protect us from every incident, of course. The point of the example is that planning around twenty days of project work already assumes nothing else will require attention. If production support is part of the team’s job, that’s quite an assumption.
Google’s Site Reliability Workbook describes operational overload as a state where urgent issues repeatedly prevent progress on key priorities. Its account is useful because it follows the consequences beyond a busy on-call shift: engineers spend less time on the projects that would make their services easier to operate.
For example, manually recovering failed jobs might be manageable each time. If those recoveries keep interrupting the work to fix the failure, though, we’ve made the recurring cost harder to remove. Adding another project to the plan doesn’t give us more capacity to do either.
Response capacity and improvement work require separate time
There’s a difference between leaving room to respond and scheduling work that reduces the number of responses required. Both require time, but treating them as interchangeable creates another problem.
If we leave a little space and call it “reliability,” production issues may consume all of it. If we schedule a fix and assume the same engineers will handle every interruption, the fix is likely to slip. We require enough flexibility to respond without repeatedly cancelling the work that improves the service.
Google’s SRE book describes a goal of keeping operational work below half of each SRE’s time, preserving at least half for engineering projects. It also distinguishes repetitive operational work from changes with lasting value. Fixing an alerting configuration, for example, is engineering work even if nobody finds it particularly glamorous.
The percentage belongs to that operating model, and copying it into every product team’s plan doesn’t make much sense. My preference is to start with the interruptions the team actually handles and check whether enough project time remains to address their causes. Honestly, if the same work keeps returning, a consistently full calendar isn’t evidence that we’re using people well.
There are times when accepting more disruption is reasonable. Launches might justify temporarily deferring improvement work, and genuinely urgent customer problems deserve attention. The decision requires acknowledging which work is being delayed, though, rather than expecting engineers to absorb it all and keep the original dates.
Before committing the next planning period, I want to know what happened to the previous one. If production work repeatedly consumed the time reserved for a fix, the next plan requires less committed scope or more capacity. Carrying the fix forward while adding another full set of promises leaves the people doing the work to reconcile the difference.